Islamabad: Capital Development Authority (CDA) here on Monday once again sought more time from the Islamabad High Court (IHC) to submit inquiry report against its own official who permitted Safa Gold Mall to construct 7 stories instead of the approved building plan of 4 stories.
Justice Aamer Farooq of the IHC while accepting CDA’s request granted time till October 10 and directed the civic body to complete inquiry report till then. Last time on August 30 CDA had also sought more time in this matter.
Meanwhile, in the civil miscellaneous application of a Cinema Owner who is constructing cinema house at the 8th story of the same building, IHC bench directed him and the mall owner to appear before CDA’s member planning for resolution of this matter. Cinema owner wants to become a party in this case.
On August 5, IHC bench at the writ petition of Safa Gold Mall, through an interim order, had conditionally allowed the mall to de-seal subject to a payment of Rs220 million payable to the CDA and removal of all encroachments in surrounding of the mall area.
CDA on July 28 had sealed the mall in the Jinnah Super Market for violating original layout plan.In this particular matter CDA has been adopting that the mall owner violated original lay out plan where he was permitted to construct 4 stories and he instead constructed 7 while 8th was under construction.
Mall owner on the other hand had adopted that he got permission from the civic body to construct more stories. CDA has been adopting that the said approval was **t granted by the CDA board that is competent authority in this matter. Further, CDA also holding an inquiry against official who permitted the mall owner to construct more stories. IHC bench previous date of hearing had directed CDA to submit inquiry report but CDA told that inquiry is still going on.
http://feeds.feedburner.com/~r/com/YEor/~4/k30B6j8T1M0
أكثر... (http://feedproxy.google.com/~r/com/YEor/~3/k30B6j8T1M0/151195-IHC-gives-more-time-to-CDA-for-submitting-inquiry-report)
Islamabad: Capital Development Authority (CDA) here on Monday once again sought more time from the Islamabad High Court (IHC) to submit inquiry report against its own official who permitted Safa Gold Mall to construct 7 stories instead of the approved building plan of 4 stories.
Justice Aamer Farooq of the IHC while accepting CDA’s request granted time till October 10 and directed the civic body to complete inquiry report till then. Last time on August 30 CDA had also sought more time in this matter.
Meanwhile, in the civil miscellaneous application of a Cinema Owner who is constructing cinema house at the 8th story of the same building, IHC bench directed him and the mall owner to appear before CDA’s member planning for resolution of this matter. Cinema owner wants to become a party in this case.
On August 5, IHC bench at the writ petition of Safa Gold Mall, through an interim order, had conditionally allowed the mall to de-seal subject to a payment of Rs220 million payable to the CDA and removal of all encroachments in surrounding of the mall area.
CDA on July 28 had sealed the mall in the Jinnah Super Market for violating original layout plan.In this particular matter CDA has been adopting that the mall owner violated original lay out plan where he was permitted to construct 4 stories and he instead constructed 7 while 8th was under construction.
Mall owner on the other hand had adopted that he got permission from the civic body to construct more stories. CDA has been adopting that the said approval was **t granted by the CDA board that is competent authority in this matter. Further, CDA also holding an inquiry against official who permitted the mall owner to construct more stories. IHC bench previous date of hearing had directed CDA to submit inquiry report but CDA told that inquiry is still going on.
http://feeds.feedburner.com/~r/com/YEor/~4/k30B6j8T1M0
أكثر... (http://feedproxy.google.com/~r/com/YEor/~3/k30B6j8T1M0/151195-IHC-gives-more-time-to-CDA-for-submitting-inquiry-report)